Peaceful Society

Proposed Plan of Action for 2003-2004

 

 

PROGRAMME

ACTIVITIES

STATUS

Women / Gender

Reviving Rural Women Front

No step taken due to lack of time, manpower and clarity about the resources,

Health Programme for Women

Continued

Documentation on Rural Women in Goa

Started

Publishing a report on Peaceful Society’s work in the field of Women Development

Partly done

Environment & Ecology

Strengthening the Indian River Network

Not much improvement due to lack of time and capable manpower

Expanding and systematizing the Medicinal Plants Development

Started well, but, progress affect due to tank work

Natural Farming work in the Campus

Continued but affected temporarily due to Tank work

Organising dialogue and various program on water conservation

Started, and plan to start a “ Centre for Promotion of Water Conservation”,

Community

 

Strengthening Work of Panchayati Raj Cell and organizing training programme for PR functionaries.

Efforts are on but not getting momentum,

Publication

Publication of “ Sarpanch” in English

PE & SD Project

Monitoring Project work as per plan

41 major task completed upto Sep 03,

Organising CBP at the national level and facilitating this processes at state / consortium level

Organised two CBP at the national level and facilitated few at state and consortium level,

Organising regional workshops on Gender

One organised for north region, 2 more are under preparation to be held in Feb for north and south region,

Organising Fellow Training

One for 7 days and second for 25 days are organised at national level,

Organising National Consultation on River Valley

Organised at Munnar on 22nd & 23rd June 03,

Organising Regional Consultation on Panchayati Raj and strengthening the Panchayati Raj work

One organised at Pune with ASA,G

Publication of SWARAJ bulletin on English, Oriya, Hindi and Malayalam

Published in Oriya and Malayalam,

Not yet started in English and Hindi

Conducting meetings of the state & consortiums

Conducted time to time,

Peace Initiative

Completion of remaining work of the project

Completed the project in May 03 and Final reports submitted to the donor.

Organisational

 

Organising meetings of the executive committee

Organised two EC meets and one of annual meet of the council,

Organising annual meeting of the council

Organised on April 19th, 03

Membership Work

Little improvement,

20 years of Peaceful Society in October 2003

Organised

Internal Evaluation of the 20 years of the Peaceful Society

Completed

Campus

Undertake Maintenance work

1.    Took repair of Cattle shed for using as common kitchen,

2.    Done painting of few rooms etc.

Improving Irrigation System

Will be undertaken after the completion of tank work,

More plantations

Successful cultivation of turmeric, took more plantation after the completion of tank work,

Dug Well

 

No need at this moment due to extension and deepening of tank,

Tank’s expansion

Started extension and deepening of tank and will be completed by 1st week of February 04,

Gandhi Museum

Not undertook, EC needs to make better plan,

 

 

<<     >>