Peaceful Society
Proposed Plan of Action for 2003-2004
|
PROGRAMME |
ACTIVITIES |
STATUS |
Women / Gender
|
Reviving Rural Women Front |
No step taken due to lack of time, manpower and clarity about the
resources, |
|
Health Programme for Women |
Continued |
|
|
Documentation on Rural Women in
Goa |
Started |
|
|
Publishing a report on Peaceful
Society’s work in the field of Women Development |
Partly done |
|
|
Environment & Ecology |
Strengthening the Indian River
Network |
Not much improvement due to lack of time and capable manpower |
|
Expanding and systematizing the
Medicinal Plants Development |
Started well, but, progress affect due to tank work |
|
|
Natural Farming work in the
Campus |
Continued but affected temporarily due to Tank work |
|
|
Organising dialogue and various
program on water conservation |
Started, and plan to start a “ Centre for Promotion of Water
Conservation”, |
|
Community
|
Strengthening Work of
Panchayati Raj Cell and organizing training programme for PR functionaries. |
Efforts are on but not getting momentum, |
|
Publication |
Publication of “ Sarpanch” in English |
|
PE & SD Project
|
Monitoring Project work as per
plan |
41 major task completed upto Sep 03, |
|
Organising CBP at the national
level and facilitating this processes at state / consortium level |
Organised two CBP at the national level and facilitated few at state
and consortium level, |
|
|
Organising regional workshops
on Gender |
One organised for north region, 2 more are under preparation to be
held in Feb for north and south region, |
|
|
Organising Fellow Training |
One for 7 days and second for 25 days are organised at national
level, |
|
|
Organising National
Consultation on River Valley |
Organised at Munnar on 22nd & 23rd June 03,
|
|
|
Organising Regional
Consultation on Panchayati Raj and strengthening the Panchayati Raj work |
One organised at Pune with ASA,G |
|
|
Publication of SWARAJ bulletin
on English, Oriya, Hindi and Malayalam |
Published in Oriya and Malayalam, Not yet started in English and Hindi |
|
|
Conducting meetings of the
state & consortiums |
Conducted time to time, |
|
Peace Initiative
|
Completion of remaining work of
the project |
Completed the project in May 03 and Final reports submitted to the
donor. |
|
Organisational |
Organising meetings of the
executive committee |
Organised two EC meets and one of annual meet of the council, |
|
Organising annual meeting of
the council |
Organised on April 19th, 03 |
|
|
Membership Work |
Little improvement, |
|
|
20 years of Peaceful Society in
October 2003 |
Organised |
|
|
Internal Evaluation of the 20
years of the Peaceful Society |
Completed |
|
|
Campus |
Undertake Maintenance work |
1. Took
repair of Cattle shed for using as common kitchen, 2. Done
painting of few rooms etc. |
|
Improving Irrigation System |
Will be undertaken after the completion of tank
work, |
|
|
More plantations |
Successful cultivation of turmeric, took more
plantation after the completion of tank work, |
|
|
Dug Well |
No need at this moment due to extension and
deepening of tank, |
|
|
Tank’s expansion |
Started extension and deepening of tank and will
be completed by 1st week of February 04, |
|
|
Gandhi Museum |
Not undertook, EC needs to make better plan, |
<< >>